Example assessment

See what stands between an offtake and a financed project.

Follow a hypothetical transaction through buyer qualification, counterparty underwriting, contract assessment, risk mitigation and monitoring.

Engagements
Transaction
Five-year take-or-pay compute offtake
Operator
GCC data centre operator
Offtaker
US AI lab
Financing
GPU facility sized against the offtake
Hypothetical. The parties, documents and findings are illustrative and do not describe a real transaction.
The assessment

Five stages, with the evidence and the open issues at each.

01
Buyer qualification
Cleared
What we checked
  • Commercial fit: stated training and inference workloads match the cluster configuration
  • Financial standing and funding capacity of the parent group
  • Ownership and control of the buyer and its shareholders
  • Regulatory eligibility of the buyer and destination
Supporting evidence
  • Parent group audited accounts
  • Shareholder funding commitment letter
  • Ownership chart to ultimate beneficial owners
Outstanding issues
  • Export licence required for the destination (carried to stage 03)
02
Counterparty underwriting
Condition
What we checked
  • The contracting entity, its capitalisation and operating history
  • Parent support and whether the parent is a party
  • Existing obligations of the group
  • Durability of the proposed payment commitments
Supporting evidence
  • Contracting entity incorporation and capitalisation documents
  • Parent financial statements and existing facilities
Outstanding issues
  • The contracting entity is newly formed and thinly capitalised
  • The parent is not a party to the agreement and has given no guarantee
03
Contract assessment
Gap
What we checked
  • Take-or-pay scope, term and commencement
  • Termination rights and payments
  • Change-in-law and export-control allocation
  • Assignment and lender protections
Supporting evidence
  • Draft five-year compute offtake agreement
  • Draft export-control and end-use certifications
Outstanding issues
  • Buyer may terminate for convenience from month 18; the termination payment covers six months of fees ($12M)
  • Take-or-pay starts only after acceptance testing, with no long-stop date
  • No lender direct agreement or step-in rights
  • Export licence risk is not allocated between the parties
04
Risk mitigation
Proposed
What we checked
  • Credit support that addresses the contracting-entity gap
  • Contract changes that close the termination and acceptance gaps
  • Insurance for the residual exposure that contract protections leave open
Supporting evidence
  • Issues from stages 01–03, each traced to the clause or document behind it
Outstanding issues
  • Parent acceptance of a guarantee or a standby letter of credit
  • Broker view on credit and political risk cover for the $10M residual
05
Monitoring
Scoped
What we checked
  • Parent and contracting-entity credit
  • Ownership and control changes
  • Licence status and regulatory changes
  • Payment performance against terms
  • Guarantee and letter of credit expiry
Supporting evidence
  • Agreed monitoring scope and reporting cycle
Outstanding issues
  • Monitoring begins at financial close
Quantified view

What the gaps are worth, and what closes them.

The exposure a lender would carry if the buyer exits at the earliest point, and the credit support sized against it.

Contract value
$120M
Unprotected exposure
$28M
Target credit support
$18M
Residual exposure
$10M
Decision
Proceed with conditions
Exposure at earliest exit
Contract value
Five years at $24M a year
$120M
Facility
70% of contract value
$84M
Outstanding at month 18
$4.5M quarterly amortisation from month 9; four payments made
$66M
Less termination payment
Six months of fees, as drafted
−$12M
Less estimated GPU recovery
See assumption 3
−$26M
Unprotected exposure
$28M
Effect of each mitigation, applied in order
Standby letter of credit
Six months of fees, from an acceptable bank, drawable on payment default
−$12M
Exposure after letter of credit
$16M
Termination payment uplift
From six to nine months of fees
−$6M
Residual exposure
For lender sizing, or the insurance view below
$10M
Not counted in the figures
Parent company guarantee
Weaker than a bank letter of credit unless the parent is rated and its financials are audited. Shown as a qualitative improvement only.
$0
Assumptions
  1. Earliest exit. The buyer terminates for convenience at month 18, the first date the draft allows, and pays the termination fee in full.
  2. Facility. $84M at 70% of contract value, with $4.5M quarterly amortisation from month 9 and a balloon at month 60.
  3. GPU recovery. Cluster cost of $65M. Month-18 resale estimated at 50% of cost ($32.5M), based on secondary-market pricing for the same hardware generation, less a 20% haircut for remarketing time and costs. Rounded to $26M.
  4. Letter of credit. Issued by a bank acceptable to the lender, for the term of the facility, drawable on payment default or termination without payment. Counted at face value.
  5. Order of mitigations. Each is applied to the exposure left by the one before it, so the effects can be read separately.
Illustrative values only. A real assessment shows the source and calculation behind each figure. The output is a financing-readiness view, not a credit approval.
Insurance view

Where insurance could close what the contract does not.

After credit support, $10M of exposure remains. We set out which covers could respond, what would trigger a claim, and what a carrier needs to see. We prepare the submission; underwriting, pricing and placement stay with licensed brokers and carriers.

Residual exposure
$10M
Candidate covers
3 + 1 optional
Insured party
The lender
Submission
Prepared by Arqis
Cover
Responds to
Exposure addressed
What the carrier needs
Credit insurance (non-payment)
Buyer fails to pay fees when due, after a waiting period
Residual $10M after LC and termination uplift
Carrier appetite for an AI lab obligor; parent financials and payment history
Political risk / export licence
Licence refused, revoked or not renewed, preventing delivery or continued service
Contract value at risk if deliveries stop
Licence status and end-use certifications; jurisdictions in scope
Contract frustration
Agreement terminated by a government act outside either party’s control
Unrecovered facility balance on frustration
Change-in-law clause and how licence risk is allocated
Residual value (optional)
GPU resale value falls below the recovery assumed in the exposure calculation
The $26M recovery assumption
Hardware generation, resale market depth and haircut evidence
Illustrative. Cover availability, terms and pricing depend on carrier appetite and are not assessed or guaranteed by Arqis.
Proposed financing conditions

Proceed, subject to four conditions and an optional insurance step.

Each condition answers an outstanding issue above. A fifth, optional step takes the residual exposure to the insurance market. Legal advice, financing decisions and insurance placement stay with the parties and their advisers.

1
Credit support
A standby letter of credit equal to six months of fees ($12M), from a bank acceptable to the lender. A parent company guarantee can be added, but is not counted as equivalent.
Stage 02
2
Termination payment
On termination for convenience, a payment of nine months of fees rather than six (+$6M).
Stage 03
3
Acceptance and long-stop
A long-stop date after which take-or-pay applies whether or not acceptance testing is complete.
Stage 03
4
Licence and lender protections
Export licence granted before first delivery, licence risk allocated in the change-in-law clause, and a lender direct agreement with step-in and cure rights.
Stages 01, 03
+
Insurance for the residual (optional)
Submission to brokers for credit and political risk cover on the $10M residual, with the lender as insured party. Placement and terms rest with licensed brokers and carriers.
Insurance view

Bring us one offtake, signed or prospective.

The output is a financing-readiness view, not a credit approval.